Walkway


List


 


 

Number of turbines 7   Av. households supplied 7,605 households
Rating of turbines 2 MW Carbon dioxide saved:    
Wind farm size 14 MW        CO2 displacement 20,174 tonnes p.a.
Predicted output 33,235 MWhr p.a.            
Note: The capacity factor used in these calculations is 27.10%.

Walkway wind farm is a Wind Prospect development of seven 2MW wind turbines within the Borough of Sedgefield in County Durham. A formal Planning Application was submitted and consented in 2005 by Sedgefield Borough Council for development.

The site is located near the villages of Sedgefield, Fishburn and Trimdon.

Discussions with local stakeholders, including Sedgefield Borough Council, and community exhibitions outlining the proposal were an important part of the development process.

To enable the project to be a locally controlled community resource, a Local Trust Fund was established via the County Durham Foundation, to be financed from a proportion of the revenue generated by the wind farm.

Following planning approval in 2005, and the subsequent discharge of planning conditions, construction of the Walkway wind farm commenced in 2007 and the project was commissioned in August 2008. 

Project Manager

James Hollender


List


 


 

Walkway construction

Bristol Website Design