|

FIRST PHASE OF CONSTRUCTION COMPLETE AT CANUNDA
4 August 2004
Following preliminary access track construction, the steel
fixers and concrete trucks have been in, completing eight
wind turbine foundations on the Canunda Wind Farm site in
South Australia. With these, the first construction phase
of the $92.5 million Canunda Wind Farm, developed by Wind
Prospect Pty Ltd and owned by International Power is now well
underway.
Wind Prospect construction manager Paul Bultitude was pleased
with the work's progress, saying:
'The Canunda Wind Farm construction is running smoothly
despite the winter weather and the challenges it brings. Our
schedule is demanding but the concrete pours are an important
benchmark in the site's progress. We're confident that the
wind farm will be commercially operational by early 2005 providing
clean, green energy to South Australian homes, particularly
those in the south-east.'
Local manufacturing firms are benefiting from the development,
with fabrication of the nacelles being carried out in Tasmania.
The first sets of blades are on their way from Denmark; and
the towers, which are being fabricated in Adelaide, are expected
to be erected in late September.
Other construction on the site - which is located at Lake
Bonney near Millicent in the south-east of South Australia
- is continuing apace, with 75% of the export transmission
line constructed, and installation of the meteorological masts
due to be completed by mid August.
On completion (expected early 2005), the wind farm will consist
of 23 Vestas 2MW wind turbines with an installed capacity
of 46MW, and generate enough electricity to supply around
25,000 average South Australian homes.
The site will be owned and operated by International Power.
Wind Prospect, the McLaren Vale based wind energy developer,
has more megawatts of wind farm projects in advanced stages
of planning and construction than any other company on mainland
Australia. The company has received planning approval for
380 MW and has a further 320MW at the planning submission
stage.
(back to top)
|